Find your District using this map.  Then click on the tabs below for project information.

 

Click the Council District tab below to find out what pavement management activities are taking place or scheduled in your area.

For a description of the process, visit our home page.

Please note that due to lower temperatures some applications may need to be delayed and/or rescheduled as some pavement applications are more temperature sensitive than others.

  • Streets between Olive Avenue and Mountain View, between 51st and 55th Avenues – Slurry seal application is currently taking place.
  • Streets in the Village Rose Community of the southeast corner of 67th Avenue and Cactus Road – Crack sealing/asphalt patching is currently taking place; followed by an application of Polymer Modified Surface Seal (PMSS) in Spring 2019.
  • Streets between Peoria Avenue and Cholla Street, from 61st Avenue to west of 59thAvenue – Crack sealing/asphalt patching is currently taking place; followed by an application of Polymer Modified Surface Seal (PMSS) in Spring 2019.
  • Streets between 51st and 55th Avenues, and between Peoria Avenue and Cholla Street – Fractured Aggregate Surface Treatment (FAST) to begin March 25th; followed by an application of Polymer Modified Surface Seal (PMSS) beginning April 8th.
  • 59th Avenue, from north of Greenway Road to Bell Road – Crack sealing/asphalt patching is currently taking place; followed by a Slurry Seal in late April.
  • Bell Road, from 51st to 59th Avenue – Crack sealing/asphalt patching is currently taking place; followed by a Slurry Seal in late April.
  • Streets from 53rd Avenue to east of 59th Avenue, north of Cactus Road in the Marshall Ranch neighborhood – – Crack sealing/asphalt patching is currently taking place; followed by an application of Polymer Modified Surface Seal (PMSS) to begin in early April.
  • Country Gables Drive, from 59th Avenue to 63rd Avenue –Thin mill and overlay is currently taking place.
  • 63rd Avenue, from Country Gables Drive to Greenway Road – Thin mill and overlay is currently taking place.  
  • Streets from Libby Street to Villa Theresa Drive, from 75th Avenue frontage road to 78thDrive in the Hidden Manor neighborhood – Polymer Modified Surface Seal (PMSS) is currently taking place.
  • 59th Avenue, from south of Eugie Avenue to Greenway Road – Remaining crack sealing/asphalt repairs to take place Sunday, March 24th; followed by a Cape Seal of Fractured Aggregate Surface Treatment (FAST) to begin March 31st; followed by a Slurry Seal application beginning April 7th.
  • Streets between 51st and 55th Avenues, and between Peoria Avenue and Cholla Street – Fractured Aggregate Surface Treatment (FAST) to begin March 25th; followed by an application of Polymer Modified Surface Seal (PMSS) beginning April 8th.
  • Eugie Avenue, from 55th to 59th Avenue – Crack sealing/asphalt patching to take place the week of March 25th; followed by a Cape Seal beginning April 1st.
  • Streets south/east of Grandview Road in Cabrillo Point, Park Paseo and Las Brisas Pointe neighborhoods – Polymer Modified Surface Seal (PMSS) application to begin late the week of March 25th.
  • 69th Avenue, from Kings Avenue to Bell Road – Polymer Modified Surface Seal (PMSS) application to begin late the week of March 25th.
  • Aire Libre Avenue, between 67th to 69th Avenues – Polymer Modified Surface Seal (PMSS) application to begin late the week of March 25th.
  • Thunderbird Road, from 51st to 59th Avenue – Cape Seal of Fractured Aggregate Surface Treatment (FAST) to begin March 31st; followed by a Slurry Seal application beginning April 7th.
  • Streets in the Arrowwood Community on the southwest corner of 67th Avenue and Greenway – Polymer Modified Surface Seal (PMSS) in late April.
  • Streets between Cactus Road and Sweetwater Avenue, between 63rd and 67th Avenues – Polymer Modified Surface Seal (PMSS) application to take place in late April/early May.
  • Cul-de-sacs of 106th Avenue and Vista Avenue off of Glen Harbor Boulevard – Fog Seal application to take place Monday, March 25th.
  • Cul-de-sacs of 108th, 109th and 110th Avenues off of Northview Avenue Fog Seal application to take place Monday, March 25th.
  • Streets north of Missouri Avenue to Montebello Avenue, from 78th Avenue to west of 75th Avenue – Double slurry seal application to begin late the week of March 25th.
  • Glendale streets between Camelback and Bethany Home Roads, west of 51st Avenue to 55th Avenue – Fractured Aggregate Surface Treatment (FAST) is currently taking place; followed by Fog Seal application to take place the week of March 25th.
  • 51st Avenue, between Camelback Road and Bethany Home Road – Slurry seal application is currently taking place.
  • Streets from Tom Murray Ave to east of 51st Avenue, and from north of Camelback Road to Colter Street  – Fractured Aggregate Surface Treatment (FAST) to take place Saturday, March 23rd; followed by Fog Seal application on Sunday, March 24th.
  • 57th and 58th Avenues, between Camelback Road and Colter Street – Fractured Aggregate Surface Treatment (FAST) is currently taking place; followed by Fog Seal application to take place the week of March 25th.
  • Glendale streets between Camelback and Bethany Home Roads, west of 51st Avenue to 55th Avenue – Fractured Aggregate Surface Treatment (FAST) is currently taking place; followed by Fog Seal application to take place the week of March 25th.
  • Glendale streets between Bethany Home Road and Maryland Avenue, between 51st and 59th Avenues – Fractured Aggregate Surface Treatment (FAST) is currently taking place; followed by Fog Seal application the week of March 25th.
  • 51st Avenue, between Camelback Road and Bethany Home Road – Slurry seal application is currently taking place.
  • Bethany Home Road, between 51st and 59th Avenue – Slurry Seal application to take place beginning March 25th.
  • Bell Road, from 51st to 59th Avenue – Crack sealing/asphalt patching is currently taking place; followed by a Slurry Seal in late April.
  • Streets north of Deer Valley Road to Pinnacle Peak Road, between 67th and 75thAvenues (excluding 71st Avenue, Patrick Lane and Hillcrest Boulevard) – Polymer Modified Surface Seal (PMSS) application to begin in early to mid-April.
  • Streets north of Beardsley Road to Deer Valley Road, between 59th and 67th Avenues (excluding Deer Valley Road and Arrowhead Loop Road where paving recently took place) – Polymer Modified Surface Seal (PMSS) application to begin in mid to late April.