Find your District using this map.  Then click on the tabs below for project information.

 

Click the Council District tab below to find out what pavement management activities are taking place or scheduled in your area.

For a description of the process, visit our home page.

No activities currently taking place or immediately scheduled.

  • Thunderbird Road, between 51st and 59th Avenues – Concrete work to prepare for cape seal is currently taking place.  

 

  • Streets from Glen Harbor Boulevard to 110th Avenue, south of Orangewood Avenue –Fog Seal application scheduled to take place Monday, November 19th through Wednesday, November 21st.

 

  • Streets from Tom Murray Ave to east of 51st Avenue, and from north of Camelback Road to Colter Street  – Fractured Aggregate Surface Treatment (FAST) scheduled to take place Saturday, November 17th and Sunday, November 18th; followed by Fog Seal application scheduled to take place Saturday, December 1st and Sunday, December 2nd.
  • Glendale streets between Camelback and Bethany Home Roads, west of 51st Avenue to 55th Avenue – Fractured Aggregate Surface Treatment (FAST) is currently scheduled to take place Monday, November 19th through Wednesday, November 21st.
  • 57th and 58th Avenues, between Camelback Road and Colter Street – Fractured Aggregate Surface Treatment (FAST ) is currently scheduled to take place Monday, November 19th through Wednesday, November 21st.
  • Streets between Glendale and Northern Avenues, between 43rd and 47th Avenues – Crack sealing is currently scheduled to begin Monday, November 26th.  

No activities currently taking place or immediately scheduled

  • Streets north of Deer Valley Road to Pinnacle Peak Road, between 67th and 75th Avenues (excluding 71st Avenue, Patrick Lane and Hillcrest Boulevard) – Crack sealing/asphalt patching is currently taking place; followed by an application of Polymer Modified Surface Seal (PMSS) in Spring 2019.